Airport/Brent Interchange Utility Relocation

Airport-Brent Utility RelocationFabre Engineering & Surveying provided water and sewer line relocation for an FDOT roadway widening Interstate Interchange project.  Our scope of services for this project included the coordination with FDOT and preparation of a utility work schedule and utility estimate summary and preparation of construction plans and specifications to relocate the utilities that conflicted with the proposed FDOT construction.  This project was completed in 2008 for Emerald Coast Utilities Authority (ECUA) and included pipe bursting 350 LF of 8-inch clay gravity sewer and Cured in Place Pipe (CIPP) lining of 100 feet of 8-inch ductile iron gravity sewer within a busy city street as part of an FDOT relocation project.  The approximate construction cost for this project was $170,000.00.